Vertical integration delayed by 18-to-24-month regulatory qualification lag

Aircraft Landing Gear Market 2025 to 2032: Supply Constraints, Backlog Economics and the Titanium Shock
What Changed

Tier-1 suppliers like Safran have acquired dedicated titanium forging assets to counter raw material shortfalls. However, newly integrated or alternative capacity requires 18 to 24 months to clear qualification and regulatory audits. This delay leaves short-term bottlenecks firmly in place, lowering projected sector CAGRs by up to 1.4%.

At a Glance
Severity
Medium
Likelihood
High
Spend Exposed
Add your annual spend to quantify exposure:
$
Confidence
90%
Recommended Actions 1

Adjust production timelines for regulatory lead times

Accounting for the 24-month qualification lag prevents unrealistic delivery expectations for components using new capacity.