DISCRETE

Electrical Conduits (Steel EMT and PVC)

Steel: tube-forming, welding, threading, galvanizing | PVC: extrusion, cutting · US
Total Cost
$6.80 / unit
Capacity (units/year)
17,000,000
Throughput %
85%
Working capital
$7.0M Mn
Capex
$10.0M Mn
Offsite
$3.0M Mn
Total investment
$20.0M Mn
Lines
12
Net raw material
$5.58
82.2%
Conversion
$1.21
17.8%
Total / unit
$6.80
$ per unit

Raw Material

$5.58 / unit
LineConsumptionUnitPrice (USD)Cost / unit
Steel coil (HRC/CRC)Livekg/unit$4.44
Zinc (galvanizing)Livekg/unit$0.20
PVC resinkg/unit$0.81
PVC additives (stabilizers, pigments, impact modifiers)kg/unit$0.14

Utility

$0.53 / unit
LineConsumptionUnitPrice (USD)Cost / unit
Electricity — fabrication & threadingMWh/unit$0.34
Electricity — PVC extrusionMWh/unit$0.19

Operating

$0.14 / unit
LinePrice (USD)Cost / unit
Direct labour — forming, threading, extrusion, finishing$0.14

Overhead

$0.33 / unit
LinePrice (USD)Cost / unit
Factory overhead (maintenance, supervisors, supplies, plant insurance)$0.14
SG&A allocation (sales, admin, compliance, working capital cost)$0.19

Depreciation

$0.06 / unit
LinePrice (USD)Cost / unit
Depreciation — production equipment and building$0.06

Others

$0.15 / unit
LinePrice (USD)Cost / unit
Packaging and outbound logistics$0.12
QA, certification, and testing (UL/CSA/IEC)$0.03